Floods push back Siddhababa tunnel opening to mid-January
Read the full story at Kathmandu Post
Plans to open the Siddhababa tunnel to traffic have been pushed back until mid-January after floods in the Bhotekoshi and Kaligandaki rivers disrupted the delivery of equipment needed to operate the tunnel. The project had aimed to allow vehicles through the tunnel before the Dashain festival. But the installation of electrical equipment and safety systems remains incomplete.
The project office now expects to open it by mid-January. China State Construction Engineering Corporation, the contractor, has been importing most of the construction materials from China. Equipment needed to operate the tunnel, including electrical components and safety systems, was also due to arrive through the Rasuwa border point.
But floods in the Bhotekoshi blocked the route, forcing the consignment to be rerouted through the Korala border point in Mustang. The delivery was further delayed when floods in the Kaligandaki washed away concrete bridges along the corridor, disrupting transport through the alternative route.
More politics
- पल्सर आरपीएम पोखरामा ३ हजारभन्दा बढी दर्शकको सहभागिताNepal Khabar
- लत्रिँदै ट्रम्पले भने : ‘निर्वाचन नतिजा स्वीकार्छु, विपक्षीसँग मिलेर काम गर्छु’Nepal Khabar
- सम्झनाका तरेलीमा सुरेशराज शर्माNepal Khabar
- आज पनि बढ्यो सुनको भाउ, चाँदीको मूल्य निरन्तर गिरावटNepal Khabar
- प्रवासी नेपालीको पुँजीलाई राष्ट्रिय विकासमा जोड्नुपर्छ: पूर्वराष्ट्रपति भण्डारीNepal Khabar
- काठमाडौँमा एकैदिन ६०८ सवारी चालकमाथि कारबाहीNepal Khabar